Delhi / Countdown begins for demolition of twin towers in Noida preparations for traffic diversion

Zoom News : Aug 24, 2022, 02:47 PM
New Delhi | The work of wiring with explosives on the floors of the Twin Towers started on Tuesday. This work will be completed by Wednesday evening. The final inspection of both the towers will be held on Thursday. On the other hand, the Noida Authority has constituted a three-member committee, which will oversee the entire work.

The tower will supervise and complete the strengthening and rescue works before demolition. This team also visited the spot on Tuesday and saw the status of work. On Thursday, the CEO of Noida Authority will also visit to take stock of the work and will hold a meeting with the concerned departments of the Authority at the Emerald Court Club.

The committee constituted by the Noida Authority includes Mukesh Vaish, senior manager of work circle-8, Praveen Salolia, senior manager of TAC and AK Varun, senior manager of water section 3. CAP Ishtiaq Ahmed will oversee the entire process. The authority's team visited the spot on Tuesday and took stock of the work. During this, the team saw the status of the work being done in the Twin Towers. After this, saw the work of repair of pillars going on in the basement of Supertech Emerald Court Society. Here the repair work of 37 pillars out of 51 has been completed. The remaining work will be completed by Wednesday or Thursday evening.

The Authority team also looked into the strength of the repair work and the arrangements made to keep the gas pipeline of GAIL safe. It was told that the gas pipeline has been covered with shed cushion. The Edifice agency claimed that the demolition would have no effect on it. After this the team inspected the exclusion zone. Also see the places where the roads will be closed by barricading. The CEO has instructed the team to keep an eye on the work coming in the demolition of the tower. If there is any blockage, remove it by coordinating with the builder, Edifice Agency, Emerald Court and RWA of AT's Village Society besides the concerned departments.

Police officers visited

DCP Rajesh S of Central Zone visited the spot on Tuesday and inspected the preparations for the security arrangements. DCP Traffic Ganesh Saha also witnessed the traffic related situation. It was told by the authority officials and the agency that all the roads in the Exclusion Zone created along the expressway, it would be necessary to close them. After the demand of the agency, the traffic police has started preparations for the diversion.

traffic diversion preparation

Preparations are being made to close the expressway roads from the expressway in front of Emerald Court to Gezha Tiraha and then turning right and then turning right to the front of the road. In this way the roads around Emerald Court and ATS Village will be closed. The gate of Parsvnath Society, which is towards ATS Green and Emerald Court, will also remain closed. Traffic coming on these roads will be barricaded in advance and stopped from Sector-108, Expressway and other sides. The final plan will be released on August 26.

SUBSCRIBE TO OUR NEWSLETTER