Jaipur. Rajasthan Government (Rajasthan Government) gave 6 big gifts to the people of the capital Jaipur, amid the ever increasing cases of Corona infection. Chief Minister Ashok Gehlot today inaugurated and laid the foundation stone of the Jaipur Development Authority's projects worth more than Rs 309 crore. The Chief Minister inaugurated and laid the foundation stone during a virtual event. The ceremony was attended by UDH Minister Shanti Dhariwal and Transport Minister Pratap Singh Adhikari. During this time, the Chief Minister also unveiled the newly installed statue of Mahatma Jyotiba Phule. This statue is installed on the twenty two godowns of Jaipur. During the function, CM Gehlot inaugurated Jahota ROB, Sitapura ROB, Bambala bridge widening work as well as Civil Lines ROB, Ramnivas Bagh Underground Parking Phase-II. Also laid the foundation of


These are 6 big gifts to the public

New statue of Mahatma Jyotiba Phule unveiled

46 lakh 78 thousand rupees spent on the statue

Statue height 9.3 feet

1050 kg weight

Octal

Jahota four lane ROB inaugurated

The cost of the project is 42 crores

Construction started on 19 May 2016

Construction completed on 28 February 2021

ROB will provide relief to Swapna Lok, Anand Lok I and II, Kaladera Industrial Area, Rampura Dabdi, Jalsu, Bhatto Ki Gali and Jahota area


Inauguration of Sitapura ROB

The cost of the project is 75 crores

Construction began 30 May 2016

Construction completed on 28 February 2021

Due to construction of ROB, traffic from Tonk Road to Sitapura, Industrial Area Agra Road will be smooth, there will be less possibility of accidents.


Inauguration of Bambala Bridge extension on Jaipur-Tonk Road

21 crore 27 lakh was spent on the project

Work started on 1 January 2017

2 March 2021 project completed

Traffic will be smooth in the southern part of the river Dravati


Foundation Stone of Four Lane ROB on Civil Lines

75 crore rupees will be spent on the project

The project will be completed on 9 October 2022

Traffic coming from Jacob Road, Jamnalal Bajaj Marg, Transport Road and Sawai Pratap Marg will get rid of traffic jam


Foundation Stone of Ramnivas Bagh Underground Parking Phase-2

94 crore 95 lakh will be spent on the project

Project to be completed by 18 August 2023

In the second phase, 1530 four-wheelers will be able to park, there will be a problem of parking in the boundary wall,

Earlier in 2013, the first phase has been built in Ramnivas Bagh,

Where 915 cars can be parked